Pepsico International Ltd.
- E/I Preventive Maintenance Contract
- Over Head Crane Project.
- Steam Line Project.
TURBOMACH Turbine 5MW
Boundary Wall Illumination & Lighting Poles
Services for Electrical & Mechanical Installations AlMaty Line at CCBPL Lahore
MV LV Switchgear and Cabling
6 x Jenbacher JGS620
3 x C1675 D5 (Cummins 11KV Diesel Gensets)
MV LV Works
4 x Jenbacher JGS620
PLC, SCADA, RTU, BATTERY BANKS
80MW Power Project
Complete Civil & Electrical Works of 132KV Switchyard ( GIS) Extension
Testing Commissioning of below cited HV Equipment
Erection, Testing & Commissioning of:
Erection, Testing & Commissioning Works at :
Assembling & Erection of Gantries in progress – NTDC Project
Under Construction – Pakistan Railways Project
Handed over successfully after complete electrical erection and assistance in testing commissioning
Completion of Civil Construction & Foundation works
2 x 50MW Wind Power Projects Gharo Sindh
Completion of civil construction, foundation & structural strengthening works at Faisalabad Plant
PPR136MW Bhikhi, NCPL 200MW, LPTL 200MW, GRPL 80MW
2 x 132KV AIS Grid stations Daska and Siranwali
(Civil, Erection, Testing & Commissioning)
Civil, Electrical Erection, Testing & Commissioning for 132/11KV
Switchyard .(Partially completed)
Erection, Testing & Commissioning Works of 132/11KV Substations.
Erection,testing and Commissioning of 250 MVA Auto Transformer at Pipri Grid Station .
22 MW CO-GENERATION POWER PROJECT–Chanar Energy Limited
ABB Power & Automation Pvt. Ltd. Pakistan
Orient Energy System
660kV HVDC Transmission Line
Matiari To Lahore |