Category : News & Updates

Switchyard Erection ,testing and commissioning at 1×22 MW BAGASSE BASED CO-GENERATION PROJECT

  • Erection & Commissioning of 2 x 25/31.5 MVA, 11/132 kV Power Transformers
  • Erection & Commissioning of 10/12.5 MVA, 11 / 6.9 kV Interconnection Transformer
  • Erection & Commissioning of 2 x 15 MVA, 11 / 0.415-0.415 kV VSD Transformer
  • Erection of Switchyard Equipment including SF6, CB’s, CT’s, VT’s, Isolators etc.
  • Installation testing and commissioning of Control, metering and Protection panel
  • Indoor & outdoor Testing and Commissioning including Protection Relays
  • Cable Laying, Termination & Testing
  • Earthing
  • Installation of Telecommunication System

Chanar Energy Limited

22 MW CO-GENERATION POWER PROJECT–Chanar Energy Limited 

  • Erection & Commissioning of MV LV Switchgear
  • Cable Laying, Termination & Testing of whole Plant
  • Erection & Commissioning of Plant Equipment’s
  • Cable Tray Works
  • Earthing System of Plant
  • Installation of Lighting System of Plant

100MW Zorlu Bahawalpur Solar power Plant

Civil, Electrical  Erection, Testing & Commissioning for 132/11KV
Switchyard .(Partially completed)

  • Foundation Works for 132/11KV Power Transformer
  • Foundation Works for 132KV AIS CB, CT & MCT
  • Foundation Works for 132KV AIS Surge Arrestor, VT
  • Civil Works for Earthing Transformer & Earth Mast Foundation
  • Construction of Fire Protection Wall
  • Construction of 132KV Switchyard Cable Trenches
  • Provision and Placing of Trench Covers
1 2