Category : Completed Projects

Switchyard Erection ,testing and commissioning at 1×22 MW BAGASSE BASED CO-GENERATION PROJECT

  • Erection & Commissioning of 2 x 25/31.5 MVA, 11/132 kV Power Transformers
  • Erection & Commissioning of 10/12.5 MVA, 11 / 6.9 kV Interconnection Transformer
  • Erection & Commissioning of 2 x 15 MVA, 11 / 0.415-0.415 kV VSD Transformer
  • Erection of Switchyard Equipment including SF6, CB’s, CT’s, VT’s, Isolators etc.
  • Installation testing and commissioning of Control, metering and Protection panel
  • Indoor & outdoor Testing and Commissioning including Protection Relays
  • Cable Laying, Termination & Testing
  • Earthing
  • Installation of Telecommunication System

Chanar Energy Limited

22 MW CO-GENERATION POWER PROJECT–Chanar Energy Limited 

  • Erection & Commissioning of MV LV Switchgear
  • Cable Laying, Termination & Testing of whole Plant
  • Erection & Commissioning of Plant Equipment’s
  • Cable Tray Works
  • Earthing System of Plant
  • Installation of Lighting System of Plant

Pipri Grid Station

Erection,testing and Commissioning of  250 MVA Auto Transformer at Pipri Grid Station .

  • Installation, Testing, Dehydration & Commissioning of 250MVA Auto Transformer at Pipri Grid Station
  • Sergi System Local parts (Supply & Installation)
1 2 3 5